Douglas J First Floor Renovation
Okemos, Michigan

Douglas J’s first-floor renovation in Okemos brought a refreshed welcome to a familiar Michigan salon. RC Contractors served as construction manager, taking the space from demolition to completion in nine weeks.
Working from plans by Studio Intrigue Architects, the team completed demolition, rough-ins and drywall, followed by new doors, trim and interior finishes. The scope included the retail and reception area, an accessible restroom and back-of-house storage. The retail area features a sculpted ceiling, accent lighting and product display walls.
Work ran from May 6 to July 5, 2024. The project continued RC’s relationship with Douglas J, supporting a repeat client with updated spaces for guests and staff.